KILROOT POWER STATION

KILROOT POWER STATION

Projects
Problem The existing boilers were over 30 years old, inefficient and getting spare parts was an on-going problem.Solution Two Cochran Equinox Pressure Jet Burners were installed which inorporate the autoflame Mk6 Micro Modulation combustion control logic. This method of control ensures that optimum combustion efficiency is achieved throughout the burner firing range and the direct drive servo motor control prevents hysteresis, which is inherent in merchanical linkage type burner plant. The Micro Modulation combustion logic also provides the capability to interface with variable speed drive control, flue gas trim and displays the boiler operating parameters in real-time.Burner Summary Rating: 29830 KG/HR Fuel: Light Oil Manufacturer: Cochran Type: Equinox Operation: Modulating Turn Down Ratio: 3.74:1
Read More
MAUDS ICE CREAM

MAUDS ICE CREAM

Projects
Problem Mauds Ice Cream plant in Carrickfergus required steam supply for new process. Solution Geoff Castles Boilers provided a turnkey supply and installation to satisfy their requirements. Servicing As well as the install we were able to supply training for Maud’s staff and total service and breakdown backup for their ongoing needs. Mauds boiler was a Control Flame rated at 450Kg/Hr.
Read More

KNOCKBRACKEN HEALTH CARE

Projects
[metaslider id=362] ProblemThe boilers needed to be installed over 200 metres of grass without the ground being disturbed. Knockbracken health care had two steam boilers which were proving to be inefficient and costly to repair. Solution A crane and truck with a lift was hired along with treaded matts to place along the grass in order to transport the boiler without damaging the premises. The two inefficient boilers were replaced with a more efficient Cochran boiler which can burn both Oil and Gas. Burner Summary Output: 2000 KG/HR Fuel: Natural Gas and Oil Working Pressure: 10 Bar G Type: Simplex Pressure Jet Combustion Control: High / Low Turn Down Ratio: 2:1
Read More
BALLYRASHANE CREAMERY

BALLYRASHANE CREAMERY

Projects
Problem The Creamery wanted to change to Natural Gas because it became available. This allowed the client to greatly reduce their fuel bills. Solution The main goal of this installation was to reduce the overall cost of fuel. This was done by installing Dual Fuel Burners oil and Gas with Electronic controls and variable speed fans. The boilers come fitted with flue gas economisers and Auto blowdown and Tds blowdown which should increase the boilers efficiency by 5 – 7%. Burner Summary Output: 2 x 5000 KG/HR Fuel: Natural Gas and Oil Working Pressure: 10 Bar G
Read More